US sponsor guide

US medical device clinical trial startup timeline

The FDA review date, hospital signature and first participant visit can fall weeks apart. Follow one illustrative US site from submission in week 0 to activation in week 9 and first enrollment in week 11.

Illustrative first-site dates

Week 0

Original IDE received and hospital contract review opens.

Week 5

Applicable FDA and IRB approvals are in place in this example.

Week 9 and week 11

Sponsor releases the site after readiness checks; the site records the first actual enrollment.

One hypothetical significant-risk investigation with one lead US site.

Work aligned withISO 14155:2026ISO 1348521 CFR Part 11GDPR

Start and finish

Choose the start and finish dates you will report

In this example, week 0 is the week FDA receives the original IDE application and the hospital starts contract review. The sponsor has already selected the lead site and prepared a submission-ready protocol. A study starting with an unfinished protocol needs a separate preparation period.

Milestone 1

Site activation

The sponsor’s documented release for the named site to recruit.

Milestone 2

First enrollment

The actual protocol-defined enrollment event for the first participant at that site. Agree the definition with the site and apply it consistently in screening records and progress reporting.

First-site schedule

Track the parallel workstreams and their release evidence

Each line gives the accountable lead, the step that must be complete and the record used for the release decision. The weeks describe one hypothetical significant-risk investigation with one lead US site. Local institutional requirements and FDA conditions can change the sequence.

Workstream and weekOwnerDependencyRecord that closes the step
Week 0 to 2 · site feasibilitySponsor feasibility lead and investigatorProtocol criteria, recent aggregate clinic volumes and availability of trained operatorsDated feasibility assessment, realistic enrollment forecast and site selection decision
Week 0 to 5 · regulatory and ethics reviewSponsor regulatory lead and site IRB coordinatorSubmission-ready protocol, device information, consent materials and the proposed siteApplicable FDA authorization, documented conditions and IRB approval covering the site and current study materials
Week 0 to 8 · contract and billingSponsor contracts lead and hospital contracting officeSchedule of assessments, site rates, coverage allocation and legal termsExecuted agreement, approved budget and agreed billing allocation
Week 2 to 8 · device and systems readinessDevice supply lead and site coordinatorQualified investigator, authorized logistics plan, storage and EDC setupDevice receipt and accountability records as applicable, access tests and named safety contacts
Week 7 to 9 · site initiation and trainingMonitor and principal investigatorCurrent approved materials, trained personnel, device and systems readinessTraining and delegation records and resolved initiation actions
Week 9 · site activationSponsor study leadAll applicable approvals, contracts and readiness records checked togetherDated site release or activation letter with the recruitment start date
Week 11 · first enrollmentPrincipal investigator and coordinatorActivated site and a participant meeting the protocol requirementsDated protocol-defined enrollment entry linked to the appropriate consent and screening records

Approval routes

Fit the regulatory workstream to the proposed investigation

Significant risk

IDE authorization and IRB approval first

Obtain FDA IDE authorization and IRB approval before beginning the investigation. For an original IDE, FDA describes approval 30 calendar days after receipt unless FDA communicates a different decision within that period. An earlier approval, conditions or disapproval can change what the sponsor may do. Keep the actual dates and any site or enrollment restrictions in the release record.

Nonsignificant risk or exempt

The IRB route

For a nonsignificant-risk investigation, the sponsor ordinarily presents its risk rationale to the reviewing IRB. If the IRB concurs and approves the study, abbreviated IDE requirements apply. For an investigation qualifying for an IDE exemption, document the specific provision and separately assess consent and IRB obligations.

Sources: FDA IDE approval process and FDA responsibilities of sponsors and investigators.

Contract delays

What happens if approval arrives before the contract?

Here the applicable FDA and IRB approvals are in place by week 5. The hospital signs in week 8, the operator completes training in week 9 and the sponsor releases the site that week. The next eligible participant enrolls in week 11.

Week 5

FDA and IRB approvals in place

Week 8

Hospital signs the agreement

Week 9

Training complete, site released

Week 11

First actual enrollment

If signature slips to week 10

The original week-9 activation is no longer feasible. The study lead checks the remaining site requirements and the next eligible clinic appointment before assigning a new enrollment date. The coordinator can document the change and its cause without promising a participant will appear in the next calendar week. These dates explain both the four-week gap from approvals to activation and the two-week gap from activation to enrollment.

Track record

The numbers behind the method

These are Eclevar’s delivered studies to date, most of them in Europe. For U.S. studies the team works with the U.S. clinical consultants shown below.

56

Studies delivered

As of November 2026

By study phase

Studies by country

France18
Germany12
United Kingdom10
Italy8
Spain6
Nordic market3
Ireland2
Other5

A study running in several countries is counted once in each country.

400+

Devices assessed by former notified body reviewers now in Eclevar leadership

9

Clinical monitors (CRAs)

4

Project managers

3

Medical writers

3

Data management and biostatistics

2

Quality assurance

Clients

Medical device manufacturers we work with

Manufacturers of implants, wound care products, monitoring systems and dental devices use Eclevar for clinical investigations, PMCF and registries. More in our client success stories.

Client: RegenLab

Multicountry prospective PMCF in wound care

A two-cohort program in chronic wounds, run across European sites under one protocol and one data model.

160

participants

14

sites

5

European countries

Client: Perouse Medical, Vygon Group

Six registered observational studies across a vascular portfolio

Eclevar structured the program architecture and supports delivery. Intended evidence use: clinical evaluation and PMCF.

6

registered observational studies

3

device families

1,150+

subjects

5 years

follow-up

Team

The people you will speak to

A small senior team, with European delivery and U.S. clinical consultants for sponsors who plan evidence on both sides of the Atlantic.

Chems Hachani

Founder and CEO

Sets the evidence strategy with the sponsor and stays accountable for delivery from first scoping call to final report.

Michael McGuffey

U.S. Clinical Consultant

Former clinical lead for final labeling on Medtronic’s Hugo robotic-assisted surgery launch team, where he helped design surgeon training and proctoring and started a clinical registry for the platform.

Dawn Heimer, PhD

U.S. Clinical and Regulatory Consultant

Provides strategic input on U.S. medical-device clinical operations, regulatory considerations and real-world evidence programs.

Karina Schönborn

Business Development Lead

Your first point of contact for scoping, budget scenarios and proposals.

Eclevar leadership includes former notified body reviewers; the full team is on the leadership page. Platinum Award · CVBF & MILO Health, xShare / EUCROF EHDS & Clinical Research Open Call. The award recognizes the submitted data use case and is not an evaluation of CRO services.

Questions

US startup questions

How long does it take to open the first US site for a device study?

In the illustrative example on this page, a site with a submission-ready protocol is activated in week 9 and enrolls its first participant in week 11, counted from the week FDA receives the original IDE application. Real timelines depend on the institution, the contract and any FDA conditions.

What is the difference between site activation and first enrollment?

Site activation is the sponsor's documented release for the named site to recruit. First enrollment is the actual protocol-defined enrollment event for the first participant at that site.

How long does FDA take to review an original IDE?

For an original IDE, FDA describes approval 30 calendar days after receipt unless FDA communicates a different decision within that period. An earlier approval, conditions or disapproval can change what the sponsor may do.

What usually delays the first site?

In the example, the hospital contract. Approvals are in place by week 5, but the agreement is signed in week 8, and a slip in signature moves activation and the enrollment date with it.

Next step

What to put in a US study startup brief

Give the startup team the protocol version, intended indication, FDA correspondence if available, candidate hospital and PI, target first-enrollment date and agreed enrollment definition. Identify who controls contract signature, investigator training, device release and system access. Ask for a named owner, next action, due date and evidence of completion for every item still open. Then build the US study budget.

We aim to respond within one business day. A confidentiality agreement can be signed before you share any document.