The FDA review date, hospital signature and first participant visit can fall weeks apart. Follow one illustrative US site from submission in week 0 to activation in week 9 and first enrollment in week 11.
Illustrative first-site dates
Week 0
Original IDE received and hospital contract review opens.
Week 5
Applicable FDA and IRB approvals are in place in this example.
Week 9 and week 11
Sponsor releases the site after readiness checks; the site records the first actual enrollment.
One hypothetical significant-risk investigation with one lead US site.
Start and finish
In this example, week 0 is the week FDA receives the original IDE application and the hospital starts contract review. The sponsor has already selected the lead site and prepared a submission-ready protocol. A study starting with an unfinished protocol needs a separate preparation period.
Milestone 1
The sponsor’s documented release for the named site to recruit.
Milestone 2
The actual protocol-defined enrollment event for the first participant at that site. Agree the definition with the site and apply it consistently in screening records and progress reporting.
First-site schedule
Each line gives the accountable lead, the step that must be complete and the record used for the release decision. The weeks describe one hypothetical significant-risk investigation with one lead US site. Local institutional requirements and FDA conditions can change the sequence.
| Workstream and week | Owner | Dependency | Record that closes the step |
|---|---|---|---|
| Week 0 to 2 · site feasibility | Sponsor feasibility lead and investigator | Protocol criteria, recent aggregate clinic volumes and availability of trained operators | Dated feasibility assessment, realistic enrollment forecast and site selection decision |
| Week 0 to 5 · regulatory and ethics review | Sponsor regulatory lead and site IRB coordinator | Submission-ready protocol, device information, consent materials and the proposed site | Applicable FDA authorization, documented conditions and IRB approval covering the site and current study materials |
| Week 0 to 8 · contract and billing | Sponsor contracts lead and hospital contracting office | Schedule of assessments, site rates, coverage allocation and legal terms | Executed agreement, approved budget and agreed billing allocation |
| Week 2 to 8 · device and systems readiness | Device supply lead and site coordinator | Qualified investigator, authorized logistics plan, storage and EDC setup | Device receipt and accountability records as applicable, access tests and named safety contacts |
| Week 7 to 9 · site initiation and training | Monitor and principal investigator | Current approved materials, trained personnel, device and systems readiness | Training and delegation records and resolved initiation actions |
| Week 9 · site activation | Sponsor study lead | All applicable approvals, contracts and readiness records checked together | Dated site release or activation letter with the recruitment start date |
| Week 11 · first enrollment | Principal investigator and coordinator | Activated site and a participant meeting the protocol requirements | Dated protocol-defined enrollment entry linked to the appropriate consent and screening records |
Approval routes
Significant risk
Obtain FDA IDE authorization and IRB approval before beginning the investigation. For an original IDE, FDA describes approval 30 calendar days after receipt unless FDA communicates a different decision within that period. An earlier approval, conditions or disapproval can change what the sponsor may do. Keep the actual dates and any site or enrollment restrictions in the release record.
Nonsignificant risk or exempt
For a nonsignificant-risk investigation, the sponsor ordinarily presents its risk rationale to the reviewing IRB. If the IRB concurs and approves the study, abbreviated IDE requirements apply. For an investigation qualifying for an IDE exemption, document the specific provision and separately assess consent and IRB obligations.
Sources: FDA IDE approval process and FDA responsibilities of sponsors and investigators.
Contract delays
Here the applicable FDA and IRB approvals are in place by week 5. The hospital signs in week 8, the operator completes training in week 9 and the sponsor releases the site that week. The next eligible participant enrolls in week 11.
Week 5
FDA and IRB approvals in place
Week 8
Hospital signs the agreement
Week 9
Training complete, site released
Week 11
First actual enrollment
The original week-9 activation is no longer feasible. The study lead checks the remaining site requirements and the next eligible clinic appointment before assigning a new enrollment date. The coordinator can document the change and its cause without promising a participant will appear in the next calendar week. These dates explain both the four-week gap from approvals to activation and the two-week gap from activation to enrollment.
Track record
These are Eclevar’s delivered studies to date, most of them in Europe. For U.S. studies the team works with the U.S. clinical consultants shown below.
56
Studies delivered
As of November 2026
By study phase
Studies by country
A study running in several countries is counted once in each country.
400+
Devices assessed by former notified body reviewers now in Eclevar leadership
9
Clinical monitors (CRAs)
4
Project managers
3
Medical writers
3
Data management and biostatistics
2
Quality assurance
Clients
Manufacturers of implants, wound care products, monitoring systems and dental devices use Eclevar for clinical investigations, PMCF and registries. More in our client success stories.







Client: RegenLab
A two-cohort program in chronic wounds, run across European sites under one protocol and one data model.
160
participants
14
sites
5
European countries
Client: Perouse Medical, Vygon Group
Eclevar structured the program architecture and supports delivery. Intended evidence use: clinical evaluation and PMCF.
6
registered observational studies
3
device families
1,150+
subjects
5 years
follow-up
Team
A small senior team, with European delivery and U.S. clinical consultants for sponsors who plan evidence on both sides of the Atlantic.

Founder and CEO
Sets the evidence strategy with the sponsor and stays accountable for delivery from first scoping call to final report.

U.S. Clinical Consultant
Former clinical lead for final labeling on Medtronic’s Hugo robotic-assisted surgery launch team, where he helped design surgeon training and proctoring and started a clinical registry for the platform.

U.S. Clinical and Regulatory Consultant
Provides strategic input on U.S. medical-device clinical operations, regulatory considerations and real-world evidence programs.

Business Development Lead
Your first point of contact for scoping, budget scenarios and proposals.
Eclevar leadership includes former notified body reviewers; the full team is on the leadership page. Platinum Award · CVBF & MILO Health, xShare / EUCROF EHDS & Clinical Research Open Call. The award recognizes the submitted data use case and is not an evaluation of CRO services.
Questions
In the illustrative example on this page, a site with a submission-ready protocol is activated in week 9 and enrolls its first participant in week 11, counted from the week FDA receives the original IDE application. Real timelines depend on the institution, the contract and any FDA conditions.
Site activation is the sponsor's documented release for the named site to recruit. First enrollment is the actual protocol-defined enrollment event for the first participant at that site.
For an original IDE, FDA describes approval 30 calendar days after receipt unless FDA communicates a different decision within that period. An earlier approval, conditions or disapproval can change what the sponsor may do.
In the example, the hospital contract. Approvals are in place by week 5, but the agreement is signed in week 8, and a slip in signature moves activation and the enrollment date with it.
Next step
Give the startup team the protocol version, intended indication, FDA correspondence if available, candidate hospital and PI, target first-enrollment date and agreed enrollment definition. Identify who controls contract signature, investigator training, device release and system access. Ask for a named owner, next action, due date and evidence of completion for every item still open. Then build the US study budget.